Zhuhai Gaolan Port District Guoneng Bulk Cargo Terminal Project's loading and unloading system and foundation engineering passed completion acceptance.

July 17, 2026
??China Transportation News
4381
Guide
Highlights at a glance
The Zhuhai Port Gaolan Coal Terminal Project, a major Guangdong infrastructure initiative, has cleared its final completion milestone. Managed by CCCC First Harbor Engineering, the project began in July 2024 and concluded in June 2026, constructing a 100,000-ton berth, two 5,000-ton berths, and handling equipment with a 1750-million-ton annual design capacity. Overcoming challenges such as typhoon risks and operational overlaps, the team implemented innovative construction methodologies, ensuring safety and quality. Post-commissioning, the terminal will significantly boost coal storage and transport capabilities in the Guangdong-Hong Kong-Macao Greater Bay Area, supporting energy needs across multiple provinces while strengthening national coal reserve infrastructure.